PMP模拟题(六)
1、项目管理方法论在国际范围内被广泛应用,当谁认同和接受这些方法时,最有利于实现项目目标?Project management methodology is used internationally; project will achieve aimness best when it is agreed upon or accept by?
A:项目经理Project manager
B: 项目团队Project team
C: 职能经理Functional manager
D:项目发起人Project sponsor
2: 在制定项目章程的过程中,项目经理确认了许多可能性很高的风险,并认为项目将会失败。适当的下一步措施是什么?
During the development of the project charter, the project manager identifies many highly probable risks and believes the project will fall. What is an appropriate next step?
A:停止为项目工作,因为风险太高
Stop working on the project as the risk is too high
B:停止制定项目章程,开始制定风险管理计划
Stop working on the project charter and start work on the risk management plan
C:继续制定项目章程,并开始制定风险管理计划
Continue working on the project charter and start work on the risk management plan
D:继续制定项目章程,然后与项目干系人一起审查项目章程
Continue working on the project charter then review it when it with the stakeholders
3: 在制定项目管理计划之前,应该确定下述哪项内容?
Which of the following should be determined before developing project management plan?
A: 项目计划更新
Project plan updates
B:干系人技能和知识
Stakeholder skills and knowledge
C:工作授权系统
Work authorization system
D: 制约因素和假设条件
Constraints and assumptions
4:在项目执行过程中,你被任命为项目经理。项目各项指标都在基线的允许范围内,如果客户对项目绩效不满意,你首先应该做什么?
You are assigned project manager in executing project; the project is in control on baseline, if customers are not satisfied with the performance, then what you should do firstly?
A:与项目团队一起讨论
Discussing with project team
B: 重新计算基线
Baseline revised
C: 重新商谈合同
Contract Renegotiation
D:与客户见面
Meeting with customers
5:项目经理将项目计划给利益相关者,并且获得他们的支持。后来,一个利益相关者说详细的交流计划需要改变。项目经理和利益相关者讨论这个计划,他们也同意项目经理给出的调整建议。接下来,项目经理应该怎么做?
A project manager presents the project plan to key stakeholders, citers stakeholder input, and obtains approvals. Later, a stakeholder says that a detail in the communications plan reeds to be changed, The project manager discusses it with stakeholder and they agree to the suggested changes.What should the project manager do next?
A: 创建附属文