CONTENT
Chapter 1 General of Project 2
Chapter 2 References 3
Chapter 3 Brief introduction of construction scheme 3
Chapter 4 Lifting Parameters Calculation 5
Chapter 5 Construction Arrangement 17
Chapter 6 Construction Preparation 19
Chapter 7 Tower Lifting 23
Chapter 8 Hoisting Security 27
Annex 1 :Crane performance parameters (CKE4000 400T Crawler crane ) 35
Annex 2 :Crane performance parameters (LTM1300 300T Truck crane ) 36
Annex 3 :The rigging Specifications Table 37
Annex 4 :The Lifting Drawing for the Deethanizer (T-230) 38
1
Chapter 1 General of Project
1.1 Project Description
Ghana GPP LPG recovery unit (Main processing area) is designed and made by the
Canada TDE company, constructed by ZPEC for the processing installation.
Deethanization unit is the key device of Ghana GPP that would complete the ethane
separation of natural gas which come from shallow sea. Dethanizer is the key
equipment of the separation process. Dethanizer hoisting is so important that can
directly impact the project overall construction schedule.
1.2 Main workload
This hoisting plan is mainly for the deethanizer、debutanizer,the tower parameters as
follows:
Equipment Equipment Tower Other
Specification and model Height Notes
NO. Name weight weights
Φ2134/3048 120.82t
T-230 dethanizer 120.82t 31.864m
显示全部