钻孔灌注桩施工技术及质量控制措施探析中图分类号:
摘要:钻孔灌注桩具有入土深、能入岩、刚度大、承载力高、桩身变形小,可方便地进行水下施工等优点,己被广泛应用到工程建设中。由于钻孔灌注桩工艺环节较多,容易出现质量事故,施工人员须保持认真的工作态度,加强对钻孔灌注桩各个环节的质量控制。本文根据笔者多年来参与工程施工的经验,就泥浆护壁钻孔灌注桩施工工艺及加强质量控制措施等问题进行探讨,期望通过与同行们相互交流,达到提高施工水平的目的。
关键词: 钻孔灌注桩; 施工工艺; 质量控制; 处理措施
Abstract: the cast-in-place pile soil into the deep, can with rock, rigidity, high bearing capacity of pile shaft and little deformation, convenient for underwater construction etc, and has been widely applied to engineering construction. Because of bored piles process more, easy to appear quality accident, construction personnel are required to keep the earnest work attitude, strengthen the cast-in-place pile of each link quality control. Based on many years’ to participate in project construction experience, slurry supporting bored pile construction process and strengthening quality control measures are discussed, and expect through and colleagues in the mutual communication, achieve the purpose of improving the construction level.
Keywords: bored piles; The construction technology; Quality control; Processing measures
中图分类号:U443.15+4文献标识码: A 文章编号:
1引言:
钻孔灌注桩是指利用钻孔机械钻出桩孔,并在孔中浇注混凝土(或先在孔中吊放钢筋笼)而成的桩。根据钻孔机械的钻头是否在土壤的含水层中施工,又分为泥浆护壁成孔和干作业成孔两种施工方法。其中泥浆护壁成孔灌注桩是桩基础施工中一种常用的方法,具有无噪音、无震动、无积压的优点,该法可防止塌孔并排出土渣而成孔,不论地下水位高低皆适用,但其施工过程部位无法直接观察,且桩的成孔制作环节很多,若某施工环节处理不好,就会造成质量问题。
2施工工艺
2#8226;1工艺流程
准备工作→钻孔机就位→钻孔→注泥浆→下套管→继续钻孔→排渣→清孔→吊放钢筋笼→射水清底→插入混凝土导管→浇筑混凝土→拔出导管→插桩顶钢筋
2#8226;2准备工作
钻机就位前应做好场地平整,挖设排水沟,设泥浆池制备泥浆,做试桩成孔,设置桩基轴线定位点和水准点,放线定桩位及复核等施工准备工作,并安装桩架及水泵设备。
2#8226;3钻孔机就位
必须保持平稳,不发生倾斜、位移,为准确控制钻孔深度,应在机架上或机管上作出控制的标尺,以便在施工中进行观测、记录。
2#8226;4钻孔及注泥浆
调直机架挺杆,对好桩位(用对位圈),开动机器钻进、出土,达到一定深度(视土质和地下水情况)停钻,孔内注入事先调制好的泥浆,然后继续进钻。
2#8226;5下套管(护筒)
孔口护筒,以起定位、保护孔口、存泥浆等作用。钻孔深度到5 m左右时,提钻下套管。
1)套管内径应大于钻头100 mm。
2)套管位置应埋设正确和稳定,套管与孔壁之间应用粘土填实,套管中心与桩孔中心线偏差不大于50 mm。
3)套管埋设深度:在粘性土中不宜小于l m,在砂土中不宜小于1#8226;5 m,并应保持孔内泥浆面高出地下水位1 m以上。
2#8226;6继续钻孔
防止表层土受振动坍塌,钻孔时不要让泥浆水位下降,当钻至持力层后,设计无特殊要求时,可继续钻深1 m左右,作为插入深度。施工中应经常测定泥浆相对
显示全部