水泥搅拌桩施工方案.pdf
目录
一、工程概况······································································································1
二、设备选型及准备工作··················································································1
三、试桩··············································································································2
四、施工工艺及质量保证措施··········································································3
五、安全保证措施及安全保证体系··································································6
六、环境保护及消防安全措施········································································10
七、施工进度计划及施工顺序········································································12
1
某高速公路某段工程第某标
深层搅拌桩施工方案
一、工程概况
1、本工程采用深层水泥搅拌桩,固化剂为32.5普通硅酸盐水
泥,桩径ø500,水泥掺入比不低于15%(每米不少于58kg)。
2、耿庄互通式立交特殊路基:A区桩长10m共计672根,B区
桩长8m共计2609根,C区桩长6m共计2390根。
3、特殊路基处理:A区桩长10m共计6017根,B区桩长8m共计1
0975根,C区桩长6m共计1461根。
4、本工程地质情况详见《岩土工程勘察报告》。
5、其它详见设计说明。
二、设备选型及施工前期准备
(一)、主要施工设备及其技术参数
根据设计要求,本工程选用SJB型深层搅拌桩机及其配套设备
进行施工,该机具有移动灵活、成桩质量高、施工速度快、噪音
低等优点,适宜本工程施工。根据总体进度安排,计划上场6台搅
拌桩机,工期4各月完成搅拌桩施工。
1、桩机型号:SJB深层搅拌机
2、搅拌头转速:60r/min
3、最大施工深度:18m
4、额定扭矩:8500N·m
2
(二)、施工前期准备
1、清除地表下各种障碍物(包括人防工程、建筑垃圾、地下
管线、电缆等)。
2、进场道路畅通,将施工用水、电接至施工现场。
3、组织材料进场,进场水泥必须具备出厂合格证,并经现场
取样送试验室复检合格,存放场地要充分满足施工需要,现场布
局合理。
(三)、测放桩位
1、施工前,首先根据轴线交叉点坐标用全站仪定出轴线。
2、根据桩位平面图及主要轴线,用经纬仪定向,钢尺量距,
确定桩位。
3、引出主要控制点于施工现场不易碾压的位置,用混凝土固
定保留。
4、测量现场地面标高,确定桩顶标高。对桩位进行编号,以
利于施工管理和资料整理。
5、设备进场后,按设计要求,在不同地点根据不同桩长进行
工艺性试验桩的施工,确定下沉及提升速度、水灰比、浆泵工作
压力、每米水泥浆用量情况等工艺参数,了解地质情况,待参数
确定后再进行工程桩施工。
三、试桩