A版次日 期审 核改 版 原 因批 准黄岛电厂2×660MW机组工程编号40XTLSEPCOBSS作 业 指 导 书
#5、6海水脱硫曝气池区
设备管道安装作业指导书
编写/日期:
单位:山东电力建设第二工程公司 锅炉工程处施工技术方案(作业指导书)报审表
表号:DJH-A-06(98版)
编号:
工程名称黄岛电厂三期2×660MW扩建工程合同编号致诚信电力工程项目监理部:
现提出曝气池区安装项目的施工技术方案(作业指导书),请予审批。
附:《#5、6曝气池区设备安装作业指导书》
施工单位(章)
负责人: 年 月 日 项目监理部意见:
项目监理部(章)
总监理师: 年 月 日
监理工程师: 年 月 日目 录
工程概述············································1
施工依据············································1
设备规格、技术参数及部件重量························1
劳力组织及工期安排··································2
施工工器具··········································2
主要施工方案········································2
曝气风机设备安装工序································4
工艺流程、要求及标准································4
安全施工措施········································9
环保注意事项········································11
十一、质量风险分析及防范措施·····························11
十二、安全风险分析及防范措施·····························11
十三、施工管理人员名单···································14
一、工程概述
黄岛电厂三期扩建工程2×660MW机组烟气脱硫工程,每台机组配备两台曝气风机,本工程共四台风机,风机采用并联运行,以便连续向海水曝气池输送氧化空气,风机以曝气池中心线对称布置在海水入口侧。该曝气风机为单级双支承结构,卧式布置。叶轮由一个整体式轴承箱支撑。油站对滑动轴承进行强制供油润滑。风机机壳两端设置了挠性联接件(围带),风机的进气箱的进口和扩压器的出口分别设置了进、排气膨胀节。电动机和风机用两个刚挠性半联轴器和一个中间轴相连接。风机的旋转方向为顺气流方向看逆时针。
经吸收塔吸收SO2后的海水在曝气池中与新的海水混合,曝气处理,使其中不稳定的亚硫酸根被氧化成为稳定的硫酸根,并使海水的PH值与COD等指标恢复到海水水质标准后排入大海。
二、编写依据
1、《曝气风机安装、运行和维护说明书》
2、《曝气池区管道安装图》(北京龙源环保工程公司、北京矿冶研究总院)
3、《电力建设施工及验收技术规范》(锅炉篇) 1996版
4、《火电施工质量检验及评定标准》(锅炉篇) 1996版
5、《电力建设安全工作规程》(火力发电厂部分)
6、《施工组织总设计》
7、《锅炉脱硫专业施工组织总设计》
三、设备规格、技术参数及部件重量
1、瀑气风机的型号:D1590-11
2、曝气风机的设计参数:
主轴转速:2980r/min 进口流量:1590 m3/min
风机升压:32KPa 进口
显示全部