历年环评工程师案例分析真题考点剖析(05-07年)(Over the years the EIA Engineer case analysis test Zhenti analysis (05-07)).doc
文本预览下载声明
历年环评工程师案例分析真题考点剖析(05-07年)(Over the years the EIA Engineer case analysis test Zhenti analysis (05-07))
China Environmental Impact Assessment net collection
China Environmental Impact Assessment net collection
make
One
Over the years the EIA Engineer exam test center analysis case analysis
An analysis of the key points of a.05 case
05 years of case analysis papers
8 questions, before
The 2 is to do the problem, all industrial cases (involving building materials, machinery items)
Second of these are industrial acceptance cases. Back
6 cases need to be chosen
4, including industrial cases
4 questions (involving)
And social services, real estate, chemicals, light industry, hazardous waste disposal), ecological cases
2 questions (involving highways, gas pipelines).
The first question (must be done) is about a cement plant expansion project.
The test sites involved include industrial policies, screening evaluation factors, determination of evaluation grades, identification of wind directions, rose charts, and evaluation
Price range, determine environmental sensitive points and protection targets, monitoring sites and so on.
The monitoring points shall be based on the requirements for wind pollution, frequency, environmental sensitive points, environmental protection targets and environmental functional areas
And the principle of uniform distribution, taking into account the arrangement of points.
2. completion acceptance monitoring - BMW Brilliance Automotive Company construction project
Second questions (must be done) is a case of industrial acceptance, mainly on the examination of enterprises containing heavy metals, fluoride, nickel and other pollutants
How should the waste water of dyeing be checked and monitored?.
The test sites concerned are to determine the monitoring scope of the completion of environmental protection facilities, and identify the first pollutants and the first pollutants
The emission standard shall be set up at the workshop discharge port, the si