ASME B31.3 Process Piping - PSIG(ASME B31.3过程管道PSIG).pdf
文本预览下载声明
ASME B31.3 Process Piping Course 12. Fabrication and Installation
ASME B31.3 Process Piping
Charles Becht IV, PhD, PE
Don Frikken, PE
Instructors
BECHT ENGINEERING COMPANY, INC. Fabrication and Installation - 1
Piping Development Process
1. Establish applicable system standard(s)
2. Establish design conditions
3. Make overall piping material decisions
Pressure Class
Reliability
Materials of construction
4. Fine tune piping material decisions
Materials
Determine wall thicknesses
Valves
5. Establish preliminary piping system layout support
configuration
6. Perform flexibility analysis
7. Finalize layout and bill of materials
8. Fabricate and install
9. Examine and test
BECHT ENGINEERING COMPANY, INC. Fabrication and Installation - 2
ASME B31.3 Process Piping Course 12. Fabrication and Installation
12. Fabrication and Installation
Welder/Brazer Qualification
Welding Processes
Weld Preparation
Typical Welds
Preheating Heat Treatment
Typical Owner Added Requirements
Installation
Flange Joints
BECHT ENGINEERING COMPANY, INC. Fabrication and Installation - 3
显示全部