Analysis on the Pre-qualification System of
Construction Project Bidding
XU Bing
Abstract: The pre-qualification is an important work in the process of bidding projects.Its aims are to choose a qualified bidder who has experience, competence, reputation to undertake the project. However, there are a lot of problems in Chinas current tender work.Based on related laws and engineering practice activities in the area of project bidding, this paper analyses the status, problems and their causes of pre-qualification in the process of project bidding. On the basis of comparing with some mature foreign practices,this paper put forward corresponding recommendations about improving Chinas pre-qualification system.
Keywords: bidding; pre-qualification; Construction Project
I. INTRODUCTION
The pre-qualification in the process of bidding projects is a activity that before sending invitation for bids or selling bidding documents,tenders inspect bidder Candidates’ qualifications,performance,skill level, financial status and so on,according with predetermined criteria of qualifications and select the qualified bidders.
One of its fundamental aims is to review whether the potential bidders have experience, competence, reputation to undertake the project. On the other hand, controlling the number of bidders in a certain range ensures that the competitive efficiency of bidding activities, and reduces the workload of the tenders evaluation.
In Chinas current tender work, on the one hand confusing the role of pre-qualification, and weakening the functions of bidding evaluation and calibration; on the other hand, there are also some defects in pre-qualification, such as non-specific applicable conditions, unclear review content, more subjective assessment method the lack of corresponding system protection and so on, which make the normative work to the pre-qualification system is very important.
II.THE EVOLUTION OF PRE-QUALIFICATION SYSTEM OF CONSTRUCTION PR