转鼓现场施工服务安装手册.pdf
ErectionManualofPOSCOSlagTreatmentProject
3Erectionofdrumequipment
Thischapterinvolvesinthemechanicalerectionofdrumequipment.
3.1Drumsupport
3.1.1Preparationwork:
Theerectionandalignmentofdrumsupportshallbeperformedwithpresence
ofthetechnicalnelundertheleadershipoftheClient.
3.1.2Erectionrequirement:
(1)Theerectionsupervisorshallinspectalltheerectiondimensionsrelated
tothehotwatertankandwillissuetheinspectionreportifallthedimensions
agreetothedrawings,shouldanydimensiondeviationisfound,remedyshall
bemadebeforestartingdrumerection.
(2)Position,alignandlevelthedrumsupportasshownonFig.1.
(3)Clearlyindicatethecentrelineonthesupportforlaterdimension
measurement.
(BlackspotonFig.1referstocentrelineandmarksaremadeatthe
correspondingportionofequipment)
(4)Casttheboltsofsupportbyquick-settingmortarassoonaspossibleafter
checkingtheerectiondimensionandlevelnessinordertofixtheboltsfor
earliererectionofdrivesanddrum.
(5)Withconcretecured(thecuringtimeshallfollowtheregulationofcivilwork
contractor),installtheidlerrollsandlevelwithadjustmentshimstoensurethe
evennessdeviationamongfouridlerrolls≤0.2mm,verticaldistance
deviationfromtheidlerrollcentretothedatumlevelwithin±0.5mm,
longitudinalcentrelinedeviationofidlerrollswithin±1mm,transversal
centrelinedeviationwithin±1mm(transversalalignmentofidlerrollscanbe
realizedviacenteringnotchontheidlerrollsupport(seeAttachmentFig1)
andthesymmetricparallelismdeviation≤0.1mm,seeFig.2.
(6)Adjusttheidlerrollstoletthemrunningfreely.