填方路基专项施工技术方案.doc
禄劝县皎平渡~马鹿塘三级公路工程挖方路基专项施工方案
PAGE
PAGE1
目录
一、第一节工程概述···································1
1、工程概况··········································1
2、沿线自然地理及工程地质条件·························1
二、第二节编制依据····································4
三、第三节工期(进度计划)、人员、机械投入················5
1、计划工期··········································5
2、人员、机械投入·······································6
四、第四节施工准备····································7
1、总公司成立了项目部,实行项目经理负责制·············7
2、施工机械化,设备精良化,管理正规化··················7
3、保证材料运输畅通、保障后勤供给······················7
4、视质量为生命,听从业主指挥,服从监理管理··············7
5、协调处理好地方关系,共建道路畅通···················8
6、加强交通安全管理,保证道路畅通······················8
五、第五节施工方案及施工方法··························8
1、施工前准备··········································8
2、测量放样·····································8
3、场地清理及填前的碾压·······························9
4、填方路基碾压······································9
六、第六节质量保证措施······························12
禄劝县皎平渡~马鹿塘三级公路工程填方路基施工专项方案
七、第七节雨季施工措施································14
八、第八节文明施工措施·······························15
九、环境保护措施····································8
十、安全保证措施····································10
PAGE1
PAGE1
填石路堤施工专项方案
第一节工程概述
一、工程概况
二、沿线自然地理及工程地质条件
1、地形地貌
路线K0+000~K1+000位于皎平渡镇山间盆地内,K1+000~K10+300沿志作箐河谷北坡展线,K10+300~K14+900沿山间凹地内展布,K14+900~K15+385位于马鹿塘乡山间盆地内,区内山脉走向受构造影响多呈近东西走向,由于河流、洪水溯源侵蚀较严重,沿志作箐河谷坡上南北向的“V”形冲沟发育。区内海拔最高点3140m(尖老包山),海拔最低点2250m(皎平渡盆地)。
不良地质及特殊性岩土
(1)K4+740~K4+770滑坡:位于线路左侧80m处,地形坡度约45~60°。滑坡体主要由残坡积硬塑状粉质黏土和强风化砂岩组成,滑坡体厚约3~10米;滑动带为岩土接合面;滑床为三迭系上统-侏罗系下统白果湾群(T3-J1bg)中风化砂岩。滑坡是在洪水冲刷侵蚀和大气降雨综合作用下形成的。后缘裂缝宽度2~5cm,坡体含水率较高,现状不稳定,尚在蠕变阶段,局部已发生滑动,滑坡滑动方向最大长度约70m,沿路线最大宽度约40m,平均厚约3m,体积约10000m3,为小型滑坡。该滑坡现处于蠕变状态,线路处于滑坡影响范围之外,可不予处理。
(2)K6+035~K6+115滑坡:位于一条现有乡村土路开挖边坡上,位于线路右60m处,地形坡度约55~65°。滑坡体主要由强风化泥岩组成,滑坡体厚约3~10米;滑动带为岩层软弱结构面;滑床为三迭系上统-侏罗系下统白果湾群(T3-J1bg)中风化砂岩。滑坡是在坡脚削方和大气降雨综合作用下形成的。该滑坡主滑方向约256°,属牵引式滑坡,现处于稳定状态。滑坡滑动方向最大长度约50m,沿路线最大宽度约50m