物业公共区域及
设施设备接管验收方案
项目名称:
文件编号
版本号
A/0
发布日期
编 制
校 对
审 核
批 准
目 录
成立接管验收小组·································2
接管验收的时间计划·······························3
物业设施设备接管工作流程图·······················4
物业设施设备接管通知·····························5
物业移交资料参考表·······························6
楼层公共部位验收表·······························11
室外公共设施验收表·······························12
消防系统验收表···································13
电梯(直梯)系统验收表····························14
电梯(扶梯)系统验收表····························16
供配电系统验收表·································19
安防系统验收表···································21
二次供水系统验收表·······························22
太阳能热水系统验收表·····························23
中央空调系统验收表·······························24
设施设备验收问题记录表···························26
物业设施设备移交清单·····························27
物业资料移交清单·································28
成立接管验收小组
组 长:
副组长:
下设三个分小组:
1、文件资料接管小组
责任人:
职责:负责接管物业的工程、设备资料的验收移交工作;业户资料的验收移交以及协助楼宇的验收移交工作;
2、现场验收接管小组
责任部门:工程维修部 客户服务部 秩序维护部 环境部
责任人:
职责:负责房屋本体、公共设施和机电设备的验收移交和钥匙接管工作。
3、财务接管小组
责任部门:
责任人:
职责:财务资料的交接。
公共区域及设备设施验收接管计划日期
公共区域及设备设施验收接管计划日期
交接项目
验收日期
整改日期
接管日期
备注(培训日期)
物业设施设备接管工作流程图
物业公司成立接管验收小组
物业公司成立接管验收小组
相关技术人员提出、明确接管验收标准
验收小组初步熟悉相关技术资料
验收小组初步熟悉相关技术资料
有 1、施工图
2、相关使用说明、维修手册等
3、产品合格证、产地证明
施工、调试阶段现场跟进
施工、调试阶段现场跟进
1、学习操作程序、规范
2、记录各种原始参数
3、存在问题及解决方法记录
就接管工作组织专题会议 由建设单位组织,监理公司、承建单
就接管工作组织专题会议
位、物业派代表参加:
明确接管范围
明确各方责任
遗留问题的解决方法
形成会议纪要分发各方
初验,核对数量、逐项检查功能
初验,核对数量、逐项检查功能