工程概况:喷漆处理线配套供电设备
Project profile: Spray paint processing line matching power supply unit
工程名称:
Project name: project
工程地点: Project location: 工程开工日期:
Project Commencement Date: 工程竣工日期:
Project Ccompletion Date:
合同内容:该项目安装设备包括:3 台高压柜,1 台 1600kVA 变压器,8 台低压开关柜,计量用互感器和计量装置。乙方负责该项目所有设备、电缆、桥架和计量装置等的电力部分的安装施工和检验工作。施工完成后,乙方负责本项目所有电力公司的相关报验、通电申请、安装验收、试验和最后通电工作。本项目为全套的交钥匙工程。本合同价格含以上全部费用(除电力部门指定由业主自己交费项目外)
The content of contract: The project equipment installation including 3 set of
high-voltage switch cabinet, one 1600 kva transformer, 8 sets of low-voltage switch cabinet, mutual inductor used metering and metering device。 Party b is responsible for installation and inspection of power part of all equipment, electric cable, bridge and metering device etc.about this project.Party B is responsible for all inspection electricity application、installation
acceptance、test and the finally electricity work related to electric power company about
this project.this project is full set of turnkey project.This contract price and above all charges。(In addition to the electric power department designated by the owner their own to pay.)
合同款: 美元
Project Funds: USD (Say only)
承包方式:合同签订后,预付款收到后 50 天完成全部安装工作,55 天时办理完项目验收工作.预付款收到后 60-65 天时保证正常通电.
Contracting type:After the contract signed,after the advance payment is received Party B will finish all the installed work in 50 days and have acceptance work of project transacted in 55 days。 Party B make sure that all the equipment will be normally electrified in 60—65 days when the advance payment is received.
付款条件(Conditions of Payment):
1。合同签订后,预付50%即 元人民币。
After the contract signed, prepay 50% of Project Funds which is ¥(RMB)。
项目通电验收后预付40%即 元人民币。
After electrified acceptance work of project finished prepay 40% o