塘沽区北塘学校办公楼维修改造施工方案[精品].doc
文本预览下载声明
目 录
第一章 编制依据···································4
第一节 编制说明································4
第二节 编制原则································4
第二章 工程概况及目标·····························6
第一节 工程简介································6
第二节 主要施工内容····························6
第三节 工期、质量目标··························6
第三章 施工平面布置及配合措施·····················6
第一节 施工平面布置·····························7
第二节 与其它施工单位配合措施···················9
第四章 施工准备···································9
第一节 技术准备································9
第二节 现场准备································10
第三节 原材料的采购供货组织、计划使用、保管····10
第五章 施工总体部署规划···························11
第一节 施工组织的特点··························11
第二节 现场条件的特点分析······················12
第三节 工程项目组织机构························12
第四节 施工各部门职责··························13
第五节 施工协调管理····························16
第六节 施工总体安排····························18
第六章 主要工程项目的施工程序和施工方法···········19
第一节 施工顺序·································19
第二节 装饰工程施工主要工艺流程·················19
第三节 主要工序的施工方法及技术措施·············19
第四节 墙面工程································20
第五节 地面工程·································20
一、橡胶地板地面
二、防水工程
三、地砖地面
第六节 涂料工程·································22
第七节 卫生间工程 ······························24
一、卫生间隔断安装
二、卫生间地面工程
第七章 施工进度计划及说明·························26
第一节 进度控制的任务···························26
第二节 进度控制的方法 ··························27
第三节 进度控制措施·····························27
第四节 施工进度(见附表一)······················28
第五节 工期保证优化措施及限期赶工措施···········29
第六节 主要材料采购要求及供应计划···············32
第七节 主要施工机械设备需用计划·················33
第八节 劳动力计划(见附表二)·····················35
第九节 节约计划·································35
第八章 工程质量目标及保证措施······················38
第一节 施工质量管理·····························38
1、施工质量控制的特点
2、施工质量控制的原则
3、施工质量因素的控制
4、施工质量控制阶段
5、工期的技术组织及保证措施
第二节 施工技术管理工作的质量控制···············50
第三节 本工程关键部位质量控制措施···············53
第九章 安全、文明施工以及环保保证措施·············54
第一节 保证安全措施·····························54
第二节 文明施工管理措施·························58
第三节 环保与环卫管理··························
显示全部