目 录
工程概况······················································2
道路参数······················································2
编制依据······················································3
设备、人员进场的措施、方法······································4
劳动力及材料进场计划··········································5
主要工程项目施工方法·········································10
施工进度计划·················································24
确保工程质量的措施···········································24
工期保证措施·················································30
雨季的施工安排···············································32
质量保证体系·················································33
文明施工和安全体系···········································36
河源市源城区龙岭工业园澳星西路和特利丰南路市政工程
施工组织设计
工程概况
项目名称:河源市源城区龙岭工业园澳星西路和特利丰南路市政工程
建设单位:河源市源城区经济技术开发有限公司
设计单位:河源市广源市政设计院
监理单位:惠州市正富建设监理有限公司
施工单位:河源鸿业市政建筑工程有限公司
工程规模:澳星西路长约504米,宽15米,用地面积7560平方米。特利
丰南路长约242米,宽15米,用地面积3630平方米。
建设内容:道路工程、排水排污等
合同造价:382.1107万元
合同工期:60日历天
二、道路参数
道路等级:支 路
质量要求:合 格
设计速度:30公里/小时
设计年限:设计使用年限为15年
道路结构形式:混凝土
断面组成为:3.0米人行道+4.5米车行道+3.0米人行道
路拱横坡度:机动车道为1.5%,人行道2%。
机动车道:22CM厚C40水泥混凝土路面(设计抗弯拉强度不小于5.0MPa)
24CM厚6%水泥稳定石屑基层
压实土基95%(E0≧30 MPa)
人行道结构:30*15*6高压机制透水砖
2CM厚1:3水泥砂浆
20CM厚4%水泥稳定石屑基层
压实土基95%
弯沉值 基层24CM厚6%水泥稳定级配石屑基层:130
土基层:≦250
三、编制依据
1、河源市源城区龙岭工业园澳星西路和特利丰南路市政工程设计图纸
2、《公路工程国内招标文件》范本2003
3、《公路路基施工技术规范》JTG F10-2006
4、《公路工程质量检验评定技术标准》JTG F80/1-2004
5、《公路工程施工安全技术规程》JTJ076-95
6、《公路工程标准施工招标文件》2009版
7、《城镇道路工程施工与质量验收规范》CJJ1-2008
四、设备、人员进场的措施、方法
1、设备、人员动员周期
人员设备的动员周期为3天,到现场时间为5天,在接到业主中标通知书后,立即进行人员、机具、设备进场准备,在与业方签订工程施工承包合同协议书的同时,7天内立即完成项目经理部建制。由项目部主要负责人带领工程技术、试验、机械、材料和行政管理人员约20人,进驻施工现场,分头进行施工准备:
1)项目经理部、工区驻地建设,包括办公场所和生活设施的到位;
2)进行地方材料和其它原材料的场地开采、采购等合同的签订;
3)安排料场、做好急用材料的进场准备;
4)进行路线的恢复定线、测量;
2、设备、人员、材料运到现场的方法
将组建项目经理部,按工程实施性施工组织设计进行精心组织,狠抓到位。
1)人员、设备到位
领导力量、技术人员、施工现场人员、管理人员准时全部到位,特别是项目经理、总工程师、质检、桥梁、道路、机械等工程项师首批到位。工程所需人员分批进驻工地。
2)工作到位
明确项目经理部的组织层次和多支施工队伍交叉作业的组织体系,界定其职责范围和协作关系,本着“职权一致,职能落实,人员精干”的原则,做到事事有人管。
3)职责到位
支持以“工期、质量、安全、效益和文明施工”为主要内容的目标考核责任制。职