PGE Data Center Baseline February 2016
2016 PGE Data Center Baseline and
Measurement and Verification (MV)
Guidelines
February 2016
CALMAC ID: PGE0369.01
Authors: Submitted to:
Taylor Engineering LLC Pacific Gas and Electric
Jeff Stein, P.E., Principal Priscilla Johnson, Ph.D., LEED O+M
Brandon Gill, P.E., Senior Engineer Expert, Strategy Analyst
PGE Data Center Baseline February 2016
Contents
CONTENTS 1
1. INTRODUCTION 3
1.1. PURPOSE3
1.2. HISTORY OF DATA CENTER BASELINE CHANGES FOR 2015 3
2. SCOPE 4
2.1. DATA CENTER AND COMPUTER ROOM DEFINITIONS 4
2.2. PROJECT TYPES IN SCOPE 4
2.2.1. New Construction 4
2.2.2. Retrofits 4
2.3. SOURCES FOR PROGRAM RULES AND REQUIREMENTS 5
3. NEW CONSTRUCTION PROJECTS 5
3.1. PROJECT ASPECTS COVERED BY TITLE 24 5
3.1.1. Title 24 Modeling Requirements6
3.1.2. Savings Calculation with Compliance Tools 6
3.1.3. Alternate Energy and Peak Demand Savings Calculation Approach 8
3.1.4. Special Requirements for Additions and Campus Plant Served Buildings 8
3.2. ELECTRICAL EQUIPMENT NOT COVERED BY TITLE 24 9
3.2.1. UPS Units 9
3.2.2. Rectifiers 12
3.2.3. Tr