新桥润新公寓小区配电工程
施
工
组
织
设
计
江苏广宇建设集团有限公司
二O一二年九月十七日
目 录
第一章 工程概况及特点
1.1工程概况······················································2
1.2工程特点······················································2
第二章 现场施工组织机构
2.1施工现场组织机构关系图········································4
2.2工程主要负责人简介············································4
第三章 施工现场总平面布置图
3.1施工现场平面布置图············································5
第四章 施工方案
4.1施工准备······················································6
4.2施工工序总体安排··············································9
4.3主要工序和特殊工序的施工方法··································9
4.4工程成本控制··················································17
第五章 工期及施工进度计划
5.1工期规划及要求················································22
5.2施工进度计划横道图············································22
第六章 质量目标、质量管理体系及技术组织措施
6.1质量目标和承诺················································23
6.2质量管理方针及目标············································23
6.3质量管理组织机构及主要职责····································24
6.4质量管理体系及质量检验的标准··································25
6.5质量管理组织措施··············································26
6.6质量保证的技术措施············································27
第七章 安全目标、安全管理体系及技术组织措施
7.1安全管理指导方针及目标········································28
7.2安全管理组织机构及主要职责····································29
7.3安全管理制度及办法············································31
7.4安全组织技术措施··············································35
7.5安全薄弱环节分析··············································37
第八章 环境保护及文明施工
8.1环境保护······················································39
8.2环境保护措施··················································39
8.3文明施工的目标、组织机构和实施方案····························40
8.4文明施工考核、管理办法········································42
第一章 工程概况及特点
1.1工程概况
1.1.1工程名称:新桥润新公寓小区配电工程
1.1.2招标单位:靖江市润新投资建设有限公司
1.1.3建设地点:靖江市新桥镇
1.1.4招标范围:
具体以施工图纸为准
设置1座开闭所,1号开闭所采用2进10出配置;采用SF6负荷开关;4台欧式箱变;户外布置,变压器与高低压室成目字型布置;规模为500KV变压器;10KV进线一回,线变组接线;0.4KV出线6回,单母线接线。
1.1.5工期要求:2012年10月30日前完工。
1.2工程特点
1.2.1、工程特点
1.2.1.1、本工程施工工期
显示全部