A, single subject
Sink hole filling pile in the cohesive soil construction when close to the pile bottom elevation of the construction method is
A. Low blow
B. heavy hammer blow
C. light hammer blow
D. Light hammer and low blow
Full marks four points
Colligation point, binding mode 2. The roof of the colligation point related to span roof forms and but be decided by the actual binding when lifting point with water
Plane Angle to satisfy
A. 30 °
B. 30 ° to 45 °
45 ° c. p
D. 60 °
Full marks four points
3. Can be anchored steel strand, steel wire, monofilament reinforced beam and beam more stout reinforced anchorage is
A. KT - Z anchor
B. JM12 anchor
C. XM type anchor
D. Screw rod anchor
Full marks four points
4. The slot type abutment and pier, the differences of pedestal
A. design principle
B. Do you need anti-slip checking
C. The size of the overturning moment
D. The size of the deformation of the pedestal
Full marks four points
5. If more than 24 m roof truss turn when acceptance of concrete cracking strength is not enough in the process of bottom chord should lower chord middle really state
A. Cushioned steel blocks
Central suspension
C. the middle part is suspended
D. both ends are suspended
Full marks four points
6. Scope of application of cold-drawn rate control method is ()
A. Rebar with furnace
B. Different furnace batches of rebar
C. Hot rolled steel
D. steel hinge line
Full marks four points
7. When parallel roof brick linoleum short side take it not less than 150 mm long side lap not less than
A. A 50 mm
B. 60 mm
C. 70 mm
D. 100 mm out four points
8. Using prestressed concrete steel strand of the strength grade should not be lower than
A. C20
B. C30
C. C40
D. C50
Out of four points
9. The level of the small block masonry mortar joint thickness and vertical mortar joint thickness is commonly
8 mm a.
10 mm B.
C. 12 mm
Out of fo