塑料排水板监理质量控制的要点
摘要:目前,在公路、水利等软地基处理类工程中,用塑料排水板来加快软土地基排水的方法已得到广泛的应用。本文以乐清纬四路工程中所采用的塑料排水板处理软土地基为背景,论述了塑料排水板的施工工艺流程,施工过程中合理控制施工质量的方法。从施工现场监理对塑料排水板的施工质量控制的角度,阐述了塑料排水板在施工中的相关问题,结合相关工程的实践经验,提出相关的质量控制对策。
关键词:塑料排水板;施工工艺;质量控制;监理;控制要点;
Abstract: At present, in the highway, water conservancy and other soft foundation treatment kinds of engineering, plastic drainage board in soft soil foundation to accelerate drainage method has been widely applied. This paper taking Le Qing Latitude four road project in the plastic drainage board in soft soil foundation treatment for the background, discusses the engineering construction process of the plastic drainage board, and reasonable construction quality control method in real engineering. From the construction site supervision on the construction quality control of plastic drainage board angle, elaborated the plastic drainage board in construction related issues, and associating with the engineering experience, puts forward some measures for quality control.
Keywords: plastic drainage board;Construction technology;Quality control;Supervision engineer;Control points;
中图分类号:O213.1文献标识码: A 文章编号:
1. 工程概况
乐清纬四路工程,其原场地原为海域,经人工吹填形成陆地,吹填厚度约6米,场地15.5米深度范围内地层主要为冲填土沉积形成的粉土、粉质粘土、淤泥质粘土层,未进行真空预压处理。其塑料排水板工程施工段路基主要为软基,共有126800m2路基使用塑料排水板处理,共计设塑料排水板1703450m。设计根据软弱土层厚度及力学指标等设计参数,对于软弱地基层厚度大于3米,填土高度大于5米的一般软弱路基地段(涵洞基底段除外),均采用塑料排水板进行治理。
2.排水原理及工法
2.1排水原理
将塑料排水板插在含水量大、压缩性高、孔隙比大的软土地基中形成竖向的排水通道,在其上铺设沙垫层作为水平排水通道。在上部辅加荷载的作用下,软土地基中产生附加应力,地基中的孔隙水应力和附加应力引起的超孔隙水应力,将天然地基A点的原有排水路径转至到竖向排水板所形成的路径[1]。随着孔隙水通过塑料排水板的排出而降低,地基的孔隙水含水量随之降低,而增加土体的密实度。进而加速地基的固结和地基土的承载力的提高,使软土地基在较短时间内达到较高的固结度,提高地基承载力、实现地基稳定的目的。如图2-1所示。
图2-1 塑料排水板排水原理示意图
2.2现场施工方法
2.2.1 插板工艺流程
测量放线→机组组装就位→插板定位→安装排水板→沉管插板→提升套管及回带量测量→剪断塑料排水板→检查→沉管提升重新装带→桩机移动就位→重复塑料排水板的插设。
2.2.2沉管插板
塑料排水板的沉管插板现场施工可概括为以下9个步骤[2]:①铺设枕木、轨道,将机器移入场内。②将排水板装入卷筒,并通过门架上的滑轮将排水板引入插杆中。③插板前检查套管垂直度,若不符合要求,前后可调节门架位置,左右可调节套管位置,保证插板垂直度在1.5%以内。④将排水板从插入杆端头引出、折回,夹上短钢筋(桩位放样时插在桩位上),用钉板机订好。⑤拉紧排水板,将插入杆对准桩位。⑥开