E-House电缆桥架安装脚手架搭设方案说明.doc
文本预览下载声明
11373-BD-NFC-3300-MS-OOO-E-0003 Page PAGE \* MERGEFORMAT 1 of 14
Bozshakol Copper Project
Clay plant
AB偏跨E-House电缆桥架安装脚手架搭设方案
Method statement of AB side building E-House cable tray installation program scaffolding erection
11373-BD-NFC-3300-MS-OOO-E-0003
0
IFR
REV#
DATE
REASON
ORIGINATOR
Li Xinhua
CHECKED
Xia Qing
APPROVED
Liu Jianhui
目 录
Content
搭设方案
1. Installation Method
风险评估
2. Risk Assessment
安全管理方案
3. Safety Management Method
一、搭设方案
Installation method
1. 概况
根据设计图纸AB偏跨内E-House下设置了2000多米电缆桥架及敷设大量的电缆,工作面相当大,工作时间持续长,而电缆桥架安装在10米的高空上,为了保障工作人员操作的安全性及不影响地面设备安装的空间,采取了以下方案搭设脚手架。
Brief
As per the design drawing, more than 2000 m cable trays and huge quantity cables shall be installed for E-house of AB side building. Beside part of the trays shall be install in 10m high place; for ensure safety of installation personnel and reduce the influence of installation of equipment on ground, the method of scaffold installation shall be adopt as mentioned below:
2. 编制依据 Codes and references
2.1 设计图纸:Design drawings
2.2 现场勘测资料 on site survey document
3. 施工准备 preparation works
3.1 技术准备 technical preparation
3.1.1 根据设计图纸及现场资料,进行图纸及资料自审和会审工作。
Self check and cross check of drawing
3.1.2 图纸及资料自审、会审后,组织施工班组熟悉施工过程及有关技术要求,结合现场实际情况集中进行一次全面技术交底。
After self check and cross check, organize the construction team to get familiar with the construction process and the relevant technical requirements, and to give a technical disclosure combined with the actual situation.
3.2 施工部署 Personnel and responsibilities
3.2.1 主要施工设备、机具准备 Equipment and tools preparation
设备进场投入使用前进行全面检修,使设备处于完好状态。
Carry out a overall inspection and maintenance to make sure all the equipment in working condition before putting in use.
脚手架的搭设
Scaffolding installation
4.1 脚手架材料检查
Inspection of materials of scaffolding