11373-BD-NFC-3300-MS-OOO-E-0003 Page PAGE \* MERGEFORMAT 1 of 14 Bozshakol Copper Project Clay plant AB偏跨E-House电缆桥架安装脚手架搭设方案 Method statement of AB side building E-House cable tray installation program scaffolding erection 11373-BD-NFC-3300-MS-OOO-E-0003 0 IFR REV# DATE REASON ORIGINATOR Li Xinhua CHECKED Xia Qing APPROVED Liu Jianhui 目 录 Content 搭设方案 1. Installation Method 风险评估 2. Risk Assessment 安全管理方案 3. Safety Management Method 一、搭设方案 Installation method 1. 概况 根据设计图纸AB偏跨内E-House下设置了2000多米电缆桥架及敷设大量的电缆,工作面相当大,工作时间持续长,而电缆桥架安装在10米的高空上,为了保障工作人员操作的安全性及不影响地面设备安装的空间,采取了以下方案搭设脚手架。 Brief As per the design drawing, more than 2000 m cable trays and huge quantity cables shall be installed for E-house of AB side building. Beside part of the trays shall be install in 10m high place; for ensure safety of installation personnel and reduce the influence of installation of equipment on ground, the method of scaffold installation shall be adopt as mentioned below: 2. 编制依据 Codes and references 2.1 设计图纸:Design drawings 2.2 现场勘测资料 on site survey document 3. 施工准备 preparation works 3.1 技术准备 technical preparation 3.1.1 根据设计图纸及现场资料,进行图纸及资料自审和会审工作。 Self check and cross check of drawing 3.1.2 图纸及资料自审、会审后,组织施工班组熟悉施工过程及有关技术要求,结合现场实际情况集中进行一次全面技术交底。 After self check and cross check, organize the construction team to get familiar with the construction process and the relevant technical requirements, and to give a technical disclosure combined with the actual situation. 3.2 施工部署 Personnel and responsibilities 3.2.1 主要施工设备、机具准备 Equipment and tools preparation 设备进场投入使用前进行全面检修,使设备处于完好状态。 Carry out a overall inspection and maintenance to make sure all the equipment in working condition before putting in use. 脚手架的搭设 Scaffolding installation 4.1 脚手架材料检查 Inspection of materials of scaffolding
显示全部
相似文档