煤矿水泵安装施工组织设计.doc
文本预览下载声明
二采区水泵房设备安装
施工组织设计
矿 长:
总 工:
安全矿长:
机电矿长:
安全副总:
机电副总:
安全管理部:
通风灭火部:
机电运输部:
审 核:
编 制:马幼君
二零一七年十一月
目 录
一、工程概况 ··································2
(一)、水泵主要································2
(二)、电控主要设备····························2
二、组织措施 ··································3
三、施工工期 ··································4
四、主要设备明细·······························4
五、施工步骤 ··································5
(一)、电控系统································5
(二)、泵体、电机及管路························5
(三)、辅助设施安装····························6
(四)、上位机系统······························6
(五)、收尾工作································6
六、调试试车···································6
七、主要安全技术措施···························7
八、主要风险管控措施···························7
附图一:泵房设备布置意识图
附图二:水泵基础图
一、工程概况
根据矿生产继续计划安排,井下二采区需安装加压水泵3台,为使此项工作安全顺利进行,特制定如下施工方案及安全技术措施,请相关区队及所有参与施工人员认真学习,并在施工中严格落实执行。
(一)、水泵主要参数
型号: MD46-50×10型多级耐磨离心泵
额定流量:46 m3/h
单级扬程:50m
安装数量:3台;
(二)、电控主要设备
1、矿用隔爆兼本安型交流变频器 3台
2、隔爆兼本安型PLC控制箱 1台
3、电气控制箱 1台
4、本安型操作台 1台
二、组织措施
1、成立设备安装领导小组
组 长:陈有宝
副组长:唐生福 张生来 杨五姓 雷转霖 孙发云
王想刚 张田录 沈承明
总指挥:孙发云
成 员:蒋天才 薛世智 孙建虎 刘敬丹 赵 龙 车小萌 马幼君 王维年 郭国峰 范顺平 谢 勇 韩悌朝
2、工作小组职责:负责施工组织设计的编制、审核;施工工作的安排;安全及工程质量的监督检查;现场竣工验收。
3、施工安排:
设备安装、泵房内各供排水管路由通灭队负责,施工人员白班作业(早7时30分至晚18时)。
(1)机电一队主要任务:电控系统设备安装、调试;动力及控制缆线敷设、达标;
(2)通灭队主要任务:泵体、电机就位安装、找正找平;各电动控制闸阀安装调试;蓄水池至三台水泵供水管路敷设安装;三台水泵至排水管路敷设安装;泵房内外其它管路敷设达标。
4、主要人员负责内容:
(1)区队人员职责:
范顺平:为此项工作现场施工总负责人,负责设备运输、吊运、安装就位、各管路安全运输、安装敷设调试设备试运转等工作的现场指挥协调,作业现场安全设施的检查、验收,合格后方可施工。
谢勇:为此项工程电控系统设备安装调试等工作。
(2)部室人员职责:
刘敬丹:为此项工作调度指挥总负责人,主要负责作业现场跟班调度指挥、工程竣工验收、设备调试运转及作业现场安全设施的监督、检查等工作。
车小萌:为此项工作现场调度指挥负责人,主要负责现场跟班调度指挥、工程竣工验收、设备调试运转及作业现场安全设施的监督、检查等工作。
三、施工工期
计划施工工期15天(白班作业),主要施工内容:三台水泵运输、安装、找正找平;电动闸阀吊装调试;供排水管路敷设、安装;电控系统设备安装调试;水泵各附属设施(上位机、交换机、各压力表、各传感器、摄像仪等)安装调试;动力及控制缆线敷设、接线;机房达标。
四、主要设备明细
序号 设备名称 规格及型号 单位 数量 备注 一、上位机部分 1 上位机 IPC-610 台 1 2 网络型硬盘录像机 NVR 台 1 含1T硬盘、22寸显示器 3 组态软件 forcecontrol 套 1 4 工业网络交换机 IES206-2GS 台 2 两光六电 5 集控软件 KJ883