【精品】农网升级改造10kV及以下电力工程竞争性谈判文件.doc
文本预览下载声明
2012年度*****第一批农网升级改造10kV及以下电力工程施工
谈判编号:******************号
谈判申请文件
投标文件内容: 技术文件
投标人: (盖投标人单位公章)
法定代表人或其委托代理人: (签字)
日 期: 2012 年 3 月 12 日
技 术 文 件 目 录
编制依据····················································1
工程概况与工程实施条件分析··································3
项目施工管理组织结构········································7
工期目标和施工进度计划·····································11
质量管理体系···············································19
安全管理体系···············································24
坏境保护与文明施工体系·····································27
工地管理和施工平面布置·····································30
施工方法与资源需求计划······································36
施工管理与协调·············································46
施工科技创新··············································54
第十二章 主要技术经济指标 ·······································58
第一章:编制依据
一、根据2012年度漳浦县每批农网升级改造10KV及以下电力工程施工工程的招标文件及招标文件提供、设计图纸及相关资料等;
二、.本工程路径地形和现场调查资料。????? 架空电力线路施工及验收规范。?????.架空送电线路施工质量检验评级标准????? 电力建设安全工作规程 (DL 5009.2-2004)电力建设安全生产工作规程 。I、II线,其中马院Π线电源接到10kv九湖线#51.新建马院I、II线双回家空闲路路径长1.342km,详细见路径走向示意图。涉及范围仅对本线路的本题涉及,对本工程涉及的路径走廊,与周围有关设施关系,林木砍划,青苗赔偿等有关协议问题,均由建设单位负责办理。建设规模如下:
2、工程量
2-1、本工程新建双回线路,路径长1.342km,采用 jklyj-10kv-240mm绝缘铝絞线路径长1.342km.
2-2、本工程治理脉高压电缆2条:YJV22-8.715KV-3*300:2*0.160km。
2-3、本工程新立Φ190-15m电杆8根,新力230-18m电杆11根,新立J30-13m四方塔3座。
2-4、本工程新装ZW32-12/TD630-20断路器1台。
2-5、本工程共拆除Φ190-15m电杆23根,隔离刀6付,避雷器3组,导线JKLYJ-185:4.026km.
2-6、本工程新做铁塔基础6座,安装6极地6组,制作电缆标志桩3个,新建电缆伸圈1个。
3、工程建设单位:**************
4、工程设计单位:漳州漳能电力勘察设计有限公司
5、工程监理单位:*************
6、工期: 30 日历天
二、施工实施条件、自然环境分析及现场调查情况说明:
1、施工实施条件、自然环境分析
1-1、安全系数:K=5
1-2、气象条件:最大风速35m/s;覆冰5mm;最低温—10.c
2、现场调查情况说明
2-1、回路数:
2-1-1、220kv马骑变10kv马院I、II线电缆采用YJV22-8.7/15kv-3*300mm,路径长0.105km.
2-1-2、220kv马骑变10kv马院I、II线#1-#12,#13--#27塔采用JKMYJ-10kv-240mm双回架设,路径长1.342km.
3、电压等级:高压10kv.
4、本工程地形地质情况:普通土80%、坚土20%。
5、本工程工地运输情况:汽车运输15km,人力平均运距0.1km。
第三章:项目施工管理组织结构
1、组织机构图(见附图一)
根据本工程的特点,为保证工程质量,确保工期,公司对本工程实行项目管理,由公司有关部门选派业务骨干,成立现场项目经理部,对本工程进