SCM-C7030 塔式起重机拆卸方案
天誉四期发展项 目工程
广东中南建设物业发展总公司
2015.1
第 0 页 共 101 页
天誉四期发展项 目 深圳市苏中九鼎机械设备有限公司
目 录
1 、通则······································································································3
2 、准备工作································································································3
2.1 工程概况································································································3
2.2 塔机型号及性能参数·················································································4
2.3 总施工流程图···························································································5
2.4 塔机安装位置平面和立面图········································································ 5
2.5 拆卸设备及工具准备··················································································6
2.6 拆卸现场准备···························································································7
2.7 塔机拆卸前检查准备··················································································7
2.8 人员准备································································································9
3 、过程控制及安全要求················································································11
3.1 目标·····································································································11
3.2 错误预防······························································································ 11
3.3 安全要求······························································································ 12
4、塔机的拆卸····························································································· 13
4.1 安装屋面吊·····························································
显示全部