(a) the lifting column
1, column and foundation elastic line, the bottom of the cup leveling
(1) the bomb line should be installed in the center line, column three column top surface pop-up line, the basic floor elevation line. A rectangular column installation according to the geometric center line center line; I-section column in rectangular part of the pop-up center line, to facilitate observation and avoid parallax, but also in the flange of a projectile with the center line of parallel lines. In addition, in the top of the column and the top bracket also install the center line pop-up roof truss and the crane beam.
Based on the cup top line is measured according to the positioning axis of the plant, and should correspond to the center line of the column installation, as column installation, alignment and calibration on the basis of.
(2) the bottom of the cup bottom of the cup leveling leveling is a check and adjust the elevation of the bottom of the cup, in order to ensure the column after lifting the top surface elevation accuracy of bracket. The adjustment method is: first, the actual measured bottom elevation of H1, the amount of up to the top of the column bottom bracket the actual length of H2; then, according to the design standard to the top surface of the bracket and the bottom of the cup H1 actual elevation difference, available at the bottom of the column to the top bracket length H3 (h3=h-h1); second, the (H3) and the actual length measured (H2) compared to get the construction error that cup bottom elevation should be adjusted value of H (h=h3-h2=h-h1-h2), and mark in the cup; finally, the construction, with 1 to 2 cement mortar or concrete with fine stones will erase the bottom of the cup to sign. In order to make the cup bottom elevation adjustment value (H) positive column construction, cup bottom elevation control values are generally lower than the design value 50mm.
For example, the column top brack