封闭母线安装及调整作业指导书.doc
文本预览下载声明
CSPC NANHAI PETROCHEMICALS PROJECT
CSPC 南海石化项目
封闭母线安装及调整
Installation and adjusting of isolated phase busbar
WORK INSTRUCTION: WI-8710-8100-0073
SEPCO Electric Power Construction Corporation
山东电力基本建设总公司
REV
版次 DATE
日期 REASON FOR ISSUE
修订原因 BY
编制 CHK’D
审核 REVIEW
审查 APPR
批准 A 8.Feb.2004 Issued for Approval Hao.BL Liu.ZX Xiao.TP Tian.GH B 21.Mar.2004 Issued for Approval Hao.BL Li.WQ Xiao.TP Tian.GH C 27.Mar.2004 Issued for Approval Hao.BL Li.WQ Xiao.TP Tian.GH D 3.Apr.2004 Issued for Approval Hao.BL Li.WQ Xiao.TP Tian.GH 00 3.May.2004 Issued for Use Hao.BL Li.WQ Xiao.TP Tian.GH
Revision information
修改记录
Rev
版次 Section No.
章节号 Description of main changes
主要修改内容 A B 2.8 Add all the section
增加整条 6.5.6.3 Add all the section 增加整条 C 6.2.5.8 Add all the section 增加整条 6.2.5.4 “24hours”should be“12 hours”将“24小时”改为“12小时”。 D 3.6 Expunge “windows and doors have been insallated.”
删掉“门窗安装完毕” 6.2.4.5 Add all the section
删掉整条 00 1.0 修改第二句和倒数第二句
Modify the second and second last sentences 2.2 改为“生产厂家提供的安装运行手册”
Should be “Vendor’s installation and commissioning manual” 3.10 Add all the section
增加整条 6.1 增加“接地”
Add “grounding” 6.2.6 Add all the section
增加整条 6.2.7 Add “Connection from the instrument header to the Air pressurization device shall be made under supervision of responsible IC engineer”
目 录
Contents
1.0 工程概况 general2.0 编制依据 references
3.0 施工准备 construction preparation
4.0 主要施工机械及工具 major machines and tools
5.0 劳动力组织 labor force
6.0 施工工序和施工方法 construction procedure and method
7.0 工作安全分析 JSA
8.0 附表 Appendix
1.0 工程概况general
CSPC 南海石化项目汽电联产工程包括5台发电机组,其中4台60MW汽轮机,1台42.3MW燃机,发电机出线连接箱至主变压器低压侧为封闭母线连接,与接地箱通过电缆连接,母线与发电机出线端连接处设一连接箱。离相式封闭母线内母直径
显示全部