七里塘水电站
10kV高压开关柜安装作业指导书
2013年9月15日
范文范例 学习指导
PAGE 10
word完美格式整理
高压开关柜安装作业指导书
目 次
1 高压开关柜安装工程简述································································· 2
2 编写依据··············································································· 2
3 作业流程··············································································· 2
4 作业方法··············································································· 3
5 质量控制措施··········································································· 5
6 单元工程质量评定表····································································· 5
附表一:固定式手车式高压开关柜安装单元工程质量评定表
附表二:互感器安装单元工程质量评定表
附表三:避雷器安装单元工程质量评定表
附表四:硬母线安装单元工程质量评定表
1 高压开关柜安装工程简述
1.1高压开关柜安装概述
本工程安装项目包括基础检查、设备开箱检查、盘柜就位安装、母线安装、断路器及隔离开关调整、交接试验。
1.2高压开关柜安装特点
七里塘水电站桥机共安装12面型号为KYN28A-12的金属铠装移开式开关柜(含2台高压限流熔断器柜),额定电压:12kV,额定绝缘水平:1min工频耐压42kV、雷冲击耐压75kV,电流参数:主母线额定电流为主变低压侧进线柜≥2500A(其余 ≥1200A)、额定短时耐受电流≥50kA/3s、额定峰值耐受电流≥125kA,防护等级:≥IP4X,耐受地震能力:Ⅷ度。安装工作在基础交面后进行。整个安装工程可分为盘柜就位安装、母线安装、断路器及隔离开关调整、交接试验。
2 编写依据
表 2-1 编 写 依 据
序号
引用资料名称
1
厂家图纸及技术文件
2
七里塘高低压设备招标文件
3
GBJ 147—1990《电气装置安装工程高压电器施工及验收规范》
4
DL 408—1991《电业安全工作规程(发电厂和变电所电气部分)》
5
DL 5009.3—1997《电力建设安全工作规程》
6
Q/CSG 10007—2004《电力设备预防性试验规程》
7
《10kV~500kV输变电及配电工程质量验收与评定标准》
8
Q/CSG 11105.2—2008《南方电网工程施工工艺控制规范》
3 作业流程
作业(工序)流程见图3-1。
图 3-1 作业(工序)流程图
4 作业方法
4.1 施工准备
4.1.1 技术准备:按规程、生产厂家安装说明书、图纸、设计要求及施工措施对施工人员进行技术交底,交底要有针对性。
4.1.2 人员组织:技术负责人、安装负责人、安全质量负责人和技术工人。
4.1.3 机具的准备:按施工要求准备机具,并对其性能及状态进行检查和维护。
4.1.4 施工材料准备:焊条、螺栓、油漆等。
4.2 基础检查
4.2.1 用经纬仪及钢卷尺对开关柜基础进行核对尺寸,检查基础槽钢长度、宽度、标高及相对位置是否符合设计要求,以及检查基础槽钢的直线度和水平度,误差不得超过允许值;检查高压及控制电缆的孔洞是否对应开关柜的排列布置。
4.2.2 清除基础槽钢面上的灰砂,完成槽钢的接地工作,测量基础槽钢的水平度和不直度,找出最高点,并标注高差,开关柜宜从中间开始就位。
4.3 搬运及开箱检查
4.3.1 现场搬运盘柜。
(1) 开关柜的搬运设专人指挥,配备足够的施工人员
显示全部